Description
TECHNICAL DATA | |
Solids Content, %: | 58 |
VOC Content, g/L: | 64 |
Color: | Green |
Flexibility @ -26° C (-15° F), ASTM C 836: | PASS |
Elongation (ASTM D 412), %: | 1000 |
Water Vapor Permeance (ASTM E 96, Procedure B) Perms: |
>15 |
Service Temperature: | Not to exceed 175° F (80° C) |
Nail Sealability (ASTM D 1970): | Pass |
Storage Temperature | 40° – 90° F (4° – 32° C) |
Air/Substrate Temperature (At Time of Application): |
20° F (-6.7° C) |
Air Leakage
Test Method | ASTM E 2178-01 | ASTM E 2357 |
Pressure: | 75 Pa (1.57 lb/ft.2) |
75 Pa (1.57 lb./ft.2) |
ABAA Requirements | 0.004 cfm/ft.2 (0.02 L/S/M2) |
0.04 cfm/ft.2 (0.2 L/S/M2) |
AIR-SHIELD TMP Results: | <0.004 cfm/ft.2 (0.02 L/S/M2) |
<0.04 cfm/ft.2 (0.2 L/S/M2) |
*Independent test available upon request
AIR-SHIELD TMP may be used in NFPA 285 complying wall assemblies. Contact W. R. MEADOWS for further information.
APPLICATION
Surface Preparation … All surfaces must be clean (free of all coatings and curing compounds), free of frost, structurally sound, and relatively smooth. Prepare substrate per manufacturer’s instruction prior to membrane application.
Exterior Sheathing Panels … Exterior sheathing panels are to be installed and fastened per manufacturer’s recommendation. For detailed application information, see INSTALLATION INSTRUCTIONS: JOINT TREATMENT OF EXTERIOR SHEATHING PANELS WHEN USING AIR-SHIELD FLUID APPLIED MEMBRANES.
Rough Openings and Protrusions … Refer to application details at wrmeadows.com for recommendations on protrusions and rough openings.
Concrete Masonry Units … Before applying AIR-SHIELD TMP to CMU surfaces, patch all cracks, protrusions, small voids, offsets, details, irregularities, and small deformities with MEADOW-PATCH® 5 or MEADOW-PATCH 20 at least two hours before application. All mortar joints should be full and struck flush with the face of the CMU.
Temperature/Conditions … Apply AIR-SHIELD TMP at air and surface temperatures of 20˚ F (-6.7° C) and higher. Curing/drying times are dependent on air temperature, airflow, relative humidity, substrate temperature, etc., specific to each individual application. Typical results at 70° (21.1° C):
Tack-Free Time: 2 hours
Full Cure: 48 hours
Roller … AIR-SHIELD TMP can be applied directly from the container; a ¾” (19.1 mm) nap roller is recommended. Apply AIR-SHIELD TMP on a vertical surface, in multiple coats if necessary, to achieve a final film thickness of 10 mils wet (6 mils dry). NOTE: While the proper film thickness may be achieved with a single coat, multiple coats may be necessary if the material slumps due to temperature and/or substrate conditions. Allow each previous coat to dry (approximately one hour) prior to applying the next coat.
Sprayer … AIR-SHIELD TMP should be stored and maintained at a temperature of 40˚ F (4.4° C) or higher throughout the entire spray application. The product will become thick and difficult to spray at temperatures below 60˚ F (15.6° C). Note: Use of Graco HydraMax 350 or Graco GH833 is recommended for optimum performance. A Graco heavy duty texture gun with either a 0.051″
(Graco GHD 551), 0.035″ (Graco GHD 535), or 0.037″ (Graco GHD 537) spray tip is recommended. If cratering occurs, the GHD 535 or 537 is recommended for a smoother finish. Spray AIR-SHIELD TMP on a vertical surface, in multiple coats if necessary, to achieve a final film thickness of 10 mils wet (6 mils dry). NOTE: While the proper film thickness may be achieved with a single coat, multiple coats may be necessary if the material slumps due to temperature and/or substrate conditions. Allow each previous coat to dry (approximately one hour) prior to applying the next coat. Porous substrates, masonry blocks, etc., may require multiple coats to achieve recommended film thickness.
Cleanup … Material should not be left in the pump, lines, or gun when finished spraying. After spraying, flush water through the system until pump and hose are clear (approximately five gallons). Aromatic solvents, such as xylene or toluene (approximately two gallons), can be used for final flushing after water is flushed through the pump and lines. Water should be flushed through the machine to remove any solvent prior to spraying of AIR-SHIELD TMP.
PRECAUTIONS
DO NOT FREEZE. Keep containers tightly sealed. Do not apply AIR-SHIELD TMP if rainfall is forecast or imminent within 12 hours of application.
HEALTH AND SAFETY
Direct contact may result in mild irritation to the skin and eyes. Should adverse effects occur, remove subject from area immediately. If irritation occurs and persists, move victim from exposure source and treat symptomatically. Flush affected areas with mild soap and water. Refer to Safety Data Sheet for complete health and safety information.
LEED INFORMATION
May help contribute to LEED credits:
- EA Credit 1: Optimize Energy Performance
- IEQ Credit 3.1: Construction IAQ Management Plan: During Construction
- IEQ Credit 4.2: Low-Emitting Materials: Paints & Coatings
- IEQ Credit 7.1: Thermal Comfort – Design
- MR Credit 2: Construction Waste Management
- MR Credit 5: Regional Materials
This material last updated January 2016.